Successful BCP/ DR of multiple processes across multiple locations for a U.S. bank

The Client

Leading US Bank

Challenge

  • Bank has outsourced over 100 processes, with more than 900 FTEs to Coforge
  • BCP and DR plans to avoid service interruptions
  • Plans had to be implemented but changed periodically as the scope and size of the operations expanded

Solution

  • Comprehensive plans based on inputs from 9+ lines of business on  RTO, Criticality of the processes
  • Teams sizes were planned and growth was managed
  • Periodic review of plans based on process changes and team size changes
  • Testing instituted to check robustness of the plans; followed by audits

Execution

Illustrative results from BCP Testing
  • Workstations unavailable test -recovered in 2hr 40 min (required RTO -6 hours)
  • Router/ Switch lost -35 mins for Router, 25 mins for Switch (RTO -1 Hour)
  • Application corrupt –50 min recovery on backup machine (RTO –1 hour)
  • Utility and backup power shutdown –1 hour 5 mins recovery using truck-mounted generator (RTO required –6 hours)

Value Delivered

No critical disruption in service (past 11 years) including during man-made emergencies (transport strike, protest rallies)